Battery storage rules: Wisconsin

Last checked against primary sources: October 28, 2026

In Wisconsin, battery storage siting is decided through local zoning by the county, city, village or (where there is no county zoning) town (Wis. Stat. 59.69, 60.61, 62.23). Separately, Wis. Stat. 196.491 requires a certificate of public convenience and necessity from the Public Service Commission (PSC) before construction of a "large electric generating facility", defined as "electric generating equipment and associated facilities designed for nominal operation at a capacity of 100 megawatts or more." The statute does not mention battery storage. The PSC's filing requirements for energy storage projects (April 7, 2026) cover stand-alone storage and storage that is part of a larger project, and say: "Proposed projects that would be large electric generating facilities as defined in Wis. Stat. § 196.491(1)(g) require a Certificate of Public Convenience and Necessity (CPCN) from the PSC." Kenosha County has battery storage zoning and has paused new approvals while it revises it.

No statewide pause; Kenosha County has paused new battery storage approvals

There is no statewide moratorium. Kenosha County adopted a pause of up to 12 months on battery storage applications and approvals in July 2026 while it revises its battery storage zoning; ask your county or city what is in effect now. Kenosha County Ord. 7 (2026); County Board minutes, July 7, 2026

Fire and building codes in force

How a project is permitted

Local zoning decides where battery storage goes: the county, city or village, or the town where there is no county zoning (Wis. Stat. 59.69, 60.61, 62.23). Wis. Stat. 196.491 requires a Public Service Commission certificate of public convenience and necessity before construction of a "large electric generating facility", "electric generating equipment and associated facilities designed for nominal operation at a capacity of 100 megawatts or more" (196.491(1)(g), (3)(a)). The statute does not mention battery storage. The PSC's filing requirements for energy storage projects (April 7, 2026) say: "Proposed projects that would be large electric generating facilities as defined in Wis. Stat. § 196.491(1)(g) require a Certificate of Public Convenience and Necessity (CPCN) from the PSC." They also ask applicants to "Provide evidence to demonstrate the proposed project would comply with NFPA 855, UL 9540 testing protocols for battery systems." Wis. Stat. 196.491(3)(i) says: "If installation or utilization of a facility for which a certificate of convenience and necessity has been granted is precluded or inhibited by a local ordinance, the installation and utilization of the facility may nevertheless proceed." Ask: is the battery 100 megawatts or more, and has the developer filed with the PSC? Ask the PSC whether it needs a certificate, and how a certificate and 196.491(3)(i) apply to your local rules. Does my county have general zoning, and is my town under it? Which fire code does my fire department enforce, and does the state fire code reach an outdoor battery yard? Ask your fire chief or the Department of Safety and Professional Services.

State permits and reporting rules that may apply

Legislation

Storage in this place

Places within

Sources

Check a specific system