The City of Maple Valley has paused battery storage permit applications since July 2025 (O-25-854), extended by O-26-870 and O-26-894. The latest extension, O-26-894, took effect July 22, 2026, for six months unless repealed sooner. Ask the city for its current status.
Maple Valley: battery storage moratorium, extended July 2026
Ordinance O-25-854 (passed July 14, 2025) set a six-month moratorium on battery storage permit applications; O-26-870 and O-26-894 extended it, the latest effective July 22, 2026 for six months unless repealed sooner. City of Maple Valley Ordinances O-25-854, O-26-870, O-26-894
Fire and building codes in force
- 2021 International Fire Code with Washington amendments (WAC 51-54A), statewide since March 15, 2024
- Proposed, not adopted: the 2024 edition, which would point energy storage rules to NFPA 855, with a planned effective date of May 3, 2027 (WSR 26-10-069)
How a project is permitted
By default, local: the city or county's zoning, conditional-use permit, SEPA review and fire code. A developer of a standalone battery may choose state certification by EFSEC instead (RCW 80.50.060(1)(b)(v)); a certificate takes the place of local permits (RCW 80.50.120(3)). Ask your city or county whether battery storage is an allowed use in your zone, and whether a moratorium is in effect and when it ends.
Sources
- City of Maple Valley Ordinance O-25-854 (moratorium) City of Maple Valley
- City of Maple Valley Ordinance O-26-894 (extension) City of Maple Valley
Check a specific system
For a proposal or a system you're evaluating, answer a few questions in BESScheck: you get the rules that apply here, a checklist of what to ask, and the sources behind each line.