In Washington your city or county decides where battery storage may go, through its zoning, conditional-use permits, environmental (SEPA) review and fire code. A developer of a standalone battery may instead choose certification by the state Energy Facility Site Evaluation Council (EFSEC); a certificate then takes the place of local permits. EFSEC is reviewing one such project now. The 2021 International Fire Code, with Washington amendments, has applied statewide since March 15, 2024; the State Building Code Council has proposed the 2024 edition, which would point energy storage rules to NFPA 855, for May 3, 2027. Some cities and counties have adopted temporary moratoriums on new battery storage applications.

No statewide pause; some cities and counties have adopted temporary pauses

There is no statewide moratorium. Some cities and counties have adopted temporary moratoriums on new battery storage applications under state planning law (six months, or up to a year with a work plan, renewable in six-month steps after a public hearing). Ask yours what is in effect now. RCW 36.70A.390, 35A.63.220; e.g. Kitsap County Ord. 645-2026, Snoqualmie Ord. 1322

Fire and building codes in force

How a project is permitted

By default, local: the city or county's zoning, conditional-use permit, SEPA review and fire code. A developer of a standalone battery may choose state certification by EFSEC instead (RCW 80.50.060(1)(b)(v)); a certificate takes the place of local permits (RCW 80.50.120(3)). Ask your city or county whether battery storage is an allowed use in your zone, and whether a moratorium is in effect and when it ends.

Legislation

Storage in this place

Places within

Sources

Check a specific system

For a proposal or a system you're evaluating, answer a few questions in BESScheck: you get the rules that apply here, a checklist of what to ask, and the sources behind each line.