Hillsboro (Washington County) paused new data center and battery storage applications for 120 days on July 27, 2026 while it writes land-use rules for both, in two phases (city page).

Hillsboro moratorium on new battery storage applications

A 120-day land-use moratorium on new data center and battery storage applications, adopted July 27, 2026, so running to November 24, 2026; the council may extend it by six months. Meanwhile the council took up Ordinance No. 6521, the first round of permanent rules: energy storage as a primary use only in industrial zones, up to 12 gross acres per site (readings October 6 and October 20, 2026). Ask the city whether it has been adopted and when it takes effect. City of Hillsboro, Data & Energy Storage in Hillsboro; City Council packets, October 6 and 20, 2026 (Ordinance No. 6521, CDCA-004-26)

Fire and building codes in force

How a project is permitted

Phase I (fall 2026): definitions, and where the uses are allowed, prohibited or limited (Ordinance No. 6521; council readings October 6 and October 20, 2026). Phase II (November 2026 to March 2027): development and design standards, which could include building height and buffers (city page). Ask the city which rules are now in effect.

Sources

Check a specific system

For a proposal or a system you're evaluating, answer a few questions in BESScheck: you get the rules that apply here, a checklist of what to ask, and the sources behind each line.