Oregon's fire code moved to the 2024 International Fire Code (IFC) on October 1, 2025 (State Fire Marshal order OSFM 6-2025). Siting runs through county or city land-use review by default; since HB 4015 (2024), a developer, or a local government after consulting the developer, may instead send a battery project to the state Energy Facility Siting Council (EFSC) (Oregon Laws 2024, ch. 25). There is no statewide pause. Marion County's zoning code says commercial battery storage is not allowed in any zone; in August 2026 the state Land Use Board of Appeals (LUBA) reversed the county's denial of a 199 MW project on farmland (LUBA No. 2026-030). Hillsboro paused new data center and battery projects in July 2026 (city page).

No statewide pause: Marion County bans battery storage; Hillsboro has a moratorium

There is no statewide pause. Siting runs through county and city land-use review, or, by election, the state Energy Facility Siting Council, so the local rules decide. LUBA No. 2026-030, p. 7; City of Hillsboro, Data & Energy Storage in Hillsboro; Oregon Laws 2024, ch. 25

Fire and building codes in force

How a project is permitted

Three tracks. (1) County or city land use by default. On farmland zoned Exclusive Farm Use, a battery has been reviewed as a "utility facility necessary for public service" (ORS 215.283(1)(c)); LUBA reversed a county denial on that question in August 2026 (LUBA No. 2026-030). Washington County approved a battery storage facility as a public utility special use on a 9.52-acre site in the AF-5 (Agriculture and Forest) district on December 17, 2025 (hearings officer order). (2) State opt-in: under ORS 469.320(8), the developer, or the local government after consulting the developer, may defer a battery project to EFSC for a state site certificate. There is no size threshold; the choice is final, and a local government cannot make it after a permit application is submitted (Oregon Laws 2024, ch. 25). (3) Part of a state-sited project: a battery covered by another energy facility's site certificate needs no separate certificate (ORS 469.320(5)). No EFSC rulemaking on battery storage found (ODOE rulemaking page and 2026 calendar).

Setbacks and spacing

Legislation