Battery storage rules: Big Stone County, MN

Last checked against primary sources: October 28, 2026

Big Stone County Renewable Energy Ordinance 26-01 (adopted July 21, 2026) applies to all areas of the county outside the incorporated limits of its cities. Utility-scale battery storage needs a conditional use permit, separate from any solar or wind permit, and is not permitted in the shoreland district or floodplain zones. The ordinance requires a 20-foot clear zone around the storage system enclosure and its screening vegetation and fencing, kept free of combustible vegetation or materials (it may be modified as part of a comprehensive emergency management plan approved by the County Board and local fire departments, and must meet any more restrictive fire and safety code requirements); signs naming the technology, any special hazards, the suppression system and a 24-hour emergency contact; safety data sheets for all components provided to the county; an emergency response plan developed with local emergency services and submitted to the Zoning Administrator; and a decommissioning plan with a bond, cash, letter of credit or escrow. Under state law a battery of 10 megawatts or more needs a Public Utilities Commission site permit unless the developer applies to the local government and receives local approval instead (Minn. Stat. 216I.05, 216I.08); ask the county how its ordinance applies to a battery of that size.

Big Stone County: utility-scale battery storage by conditional use permit (July 2026)

Ordinance 26-01 (July 21, 2026) requires a conditional use permit for utility-scale battery storage in the unincorporated county, keeps it out of the shoreland district and floodplain zones, and sets 1,320-foot setbacks from dwellings and property lines. Big Stone County Ord. 26-01; County Board minutes, July 21, 2026

Fire and building codes in force

How a project is permitted

A battery of 10 megawatts or more (nameplate) needs a Public Utilities Commission site permit (Minn. Stat. 216I.05 subd. 1(a)). The developer may instead apply to the local governments with jurisdiction: "If local approval is granted, a site or route permit is not required from the commission. If the applicant files an application with the commission, the applicant waives the applicant's right to seek local approval for the project" (216I.08 subd. 1(a)). A local government the developer has applied to may request that the Commission assume jurisdiction, within 60 days of the date the developer files an application with any one local government, and jurisdiction then transfers to the Commission (216I.08 subd. 1(b)). A Commission permit "supersedes and preempts all zoning, building, or land use rules, regulations, or ordinances promulgated by regional, county, local and special purpose government" (216I.18 subd. 1), but the permittee "must obtain state permits that may be required" (subd. 2). Below 10 megawatts, no Commission permit is required, and the developer "must (1) obtain any approval required by local, state, or federal units of government with jurisdiction over the project" (216I.10). Ask: is the battery 10 megawatts or more, and has the developer applied to the Commission or to the county or city? If it applied locally, is the county or city asking the Commission to take it? Which local building and fire permits does the developer expect to need? Which fire code and edition does your fire department enforce?

State permits and reporting rules that may apply

Setbacks and spacing

Sources

Check a specific system

For a proposal or a system you're evaluating, answer a few questions in BESScheck: you get the rules that apply here, a checklist of what to ask, and the sources behind each line.