Battery storage rules: Minnesota

Last checked against primary sources: October 28, 2026

Minnesota's Energy Infrastructure Permitting Act (Minn. Stat. ch. 216I, in effect July 1, 2025) defines an "energy storage system" as "equipment and associated facilities designed with a nameplate capacity of 10,000 kilowatts or more that is capable of storing generated electricity for a period of time and delivering the electricity for use after storage" (216I.02 subd. 6), and says: "A person is prohibited from constructing ... an energy storage system ... without a site permit issued by the commission" (216I.05 subd. 1(a)). A developer may instead apply to the local governments with jurisdiction: "If local approval is granted, a site or route permit is not required from the commission" (216I.08 subd. 1(a)). A local government the developer has applied to may request that the Public Utilities Commission assume jurisdiction, within 60 days of the date the developer files an application with any one local government, and jurisdiction then transfers to the Commission (216I.08 subd. 1(b)). A Commission permit "supersedes and preempts all zoning, building, or land use rules, regulations, or ordinances promulgated by regional, county, local and special purpose government" (216I.18). Below 10 megawatts no Commission permit is required, and local, state and federal approvals apply (216I.10). The state fire code is based on the 2018 International Fire Code.

No statewide pause

There is no statewide moratorium. Counties, cities and towns (townships) can adopt a temporary pause, called an interim ordinance; ask your county, city or township whether one covers battery storage and when it ends. Minn. Stat. 394.34 (counties), 462.355 subd. 4 (cities and towns)

Fire and building codes in force

How a project is permitted

A battery of 10 megawatts or more (nameplate) needs a Public Utilities Commission site permit (Minn. Stat. 216I.05 subd. 1(a)). The developer may instead apply to the local governments with jurisdiction: "If local approval is granted, a site or route permit is not required from the commission. If the applicant files an application with the commission, the applicant waives the applicant's right to seek local approval for the project" (216I.08 subd. 1(a)). A local government the developer has applied to may request that the Commission assume jurisdiction, within 60 days of the date the developer files an application with any one local government, and jurisdiction then transfers to the Commission (216I.08 subd. 1(b)). A Commission permit "supersedes and preempts all zoning, building, or land use rules, regulations, or ordinances promulgated by regional, county, local and special purpose government" (216I.18 subd. 1), but the permittee "must obtain state permits that may be required" (subd. 2). Below 10 megawatts, no Commission permit is required, and the developer "must (1) obtain any approval required by local, state, or federal units of government with jurisdiction over the project" (216I.10). Ask: is the battery 10 megawatts or more, and has the developer applied to the Commission or to the county or city? If it applied locally, is the county or city asking the Commission to take it? Which local building and fire permits does the developer expect to need? Which fire code and edition does your fire department enforce?

State permits and reporting rules that may apply

Legislation

Storage in this place

Places within

Sources

Check a specific system

For a proposal or a system you're evaluating, answer a few questions in BESScheck: you get the rules that apply here, a checklist of what to ask, and the sources behind each line.