The Town of Cortlandt has paused new battery storage since 2024. Local Law 1 of 2026, adopted July 21, 2026, extends the moratorium through December 31, 2026, unless the Town ends it sooner. A committee has drafted a battery storage law, and the Town Board chose to allow the State to issue additional guidance. Ask the Town for its current status.

Cortlandt: moratorium on new battery storage through December 31, 2026

Local Law 1 of 2026 (adopted July 21, 2026, Resolution 168-26) extends the Town's moratorium on new battery storage through December 31, 2026, unless terminated earlier. A committee has drafted a battery storage law, and the Board chose to allow the State to issue additional guidance. The pause began with Local Law 2 of 2024. Town of Cortlandt Local Law 1 of 2026 (Resolution 168-26)

Fire and building codes in force

How a project is permitted

Standalone storage: local zoning (town, village or city) plus a building permit under the Uniform Code from the local code enforcement office. Storage co-located with, and storing energy from, a renewable generator of 25 MW or more goes through the state Office of Renewable Energy Siting (Public Service Law §137(4)). NYSERDA's Battery Energy Storage System Guidebook (February 2026) offers a model law and permit; it is advisory, and its model law leaves setbacks for larger systems to the zoning district. Ask your town whether its zoning addresses battery storage and whether a moratorium is in effect.