Battery storage rules: Comstock Charter Township (Kalamazoo County), MI

Last checked against primary sources: October 27, 2026

Comstock Township's earlier pause (Ordinances 550 and 552) ended, and Ordinance 564 (adopted December 15, 2025) allows large battery storage (50 MW or more) by special land use in the LM and M districts and a large-system overlay (at least 140 acres), and smaller systems by special exception in LM and M. It requires a 15 ft height limit, 55 average hourly dBA at a neighbouring non-participating property line, NFPA 855, fire and emergency response plans prepared in consultation with responders and approved by the Fire Chief, a hazard mitigation analysis (updated if the battery chemistry changes), and decommissioning with financial assurance. Ask the township for its current status.

Comstock Township: battery storage ordinance adopted December 2025; the pause ended

Ordinance 564 (December 15, 2025) allows large battery storage by special land use in the LM and M districts and a large-system overlay (smaller systems by special exception), with setbacks up to 2,000 ft from schools, hospitals, assisted living and child care. Comstock Township Ordinance 564

Fire and building codes in force

How a project is permitted

Local zoning by default. For a project of 50 MW and 200 MWh or more, the developer may apply to the Michigan Public Service Commission for a siting certificate, and a local unit with zoning may ask the Commission to require one (MCL 460.1222). Ask: does my township have an ordinance for battery storage, or a moratorium? Which fire code and edition does my fire authority enforce? Is a project of this size handled by the township or eligible for the state Commission?

Setbacks and spacing

Sources

Check a specific system

For a proposal or a system you're evaluating, answer a few questions in BESScheck: you get the rules that apply here, a checklist of what to ask, and the sources behind each line.