Last checked against primary sources: October 27, 2026

Massachusetts has one statewide fire code, 527 CMR 1.00, based on NFPA 1 (2021) with Massachusetts amendments; its Chapter 52 references NFPA 855 (2020 edition). The head of the local fire department issues the permit for energy storage above NFPA 855's threshold quantities (MassDEP gives 20 kWh for lithium-ion). Under the 2024 climate law, projects of 100 MWh or more get one consolidated permit from the Energy Facilities Siting Board; smaller projects are permitted by the town, and if the developer chooses a consolidated local permit, the town must accept it (from October 1, 2026) and decide within 12 months. The Attorney General reads the state zoning law (G.L. c. 40A §3) to protect battery storage from prohibition or unreasonable regulation, and has disapproved town moratoriums and stand-alone bans while approving regulatory bylaws.

No statewide pause; the Attorney General has disapproved town moratoriums

The 2024 climate law has no moratorium provision. The Attorney General, who reviews town bylaws, has disapproved town moratoriums on battery storage under G.L. c. 40A §3 (for example Northfield, 2024, and Blandford, 2026), and has approved bylaws that regulate it (for example Wilbraham, 2024). Attorney General Municipal Law Unit decisions: Northfield #11346, Blandford #12153, Wilbraham #11474

Fire and building codes in force

How a project is permitted

Projects of 100 MWh or more: one consolidated permit from the Energy Facilities Siting Board (rules apply to filings from July 1, 2026; the Board must decide within 15 months of finding the application complete). Smaller projects: the town's zoning and permits; the developer may choose a consolidated local permit, which the town must decide within 12 months or issue a constructive approval permit, and every town must accept that application from October 1, 2026 (Chapter 239 of the Acts of 2024; 225 CMR 29.00). Ask your town how its zoning treats battery storage and which tier your project falls in.

Legislation

Storage in this place

Places within

Sources

Check a specific system

For a proposal or a system you're evaluating, answer a few questions in BESScheck: you get the rules that apply here, a checklist of what to ask, and the sources behind each line.