Battery storage rules: San Diego County, CA

Last checked against primary sources: October 23, 2026

The Board of Supervisors declined a blanket moratorium, choosing enhanced safety reviews and interim standards instead. The May 2024 Otay Mesa / Gateway indoor fire (contained to 1 of 7 buildings) informs the county's proportionate standards.

San Diego County: no moratorium; County Fire requires 100 ft from homes

The Board did not adopt a moratorium (September 11, 2024) and directed County Fire to develop standards instead. County Fire's BESS guidelines (September 17, 2026, no longer interim) require battery systems to be 100 ft from lot lines with residential, educational or institutional occupancies. A draft county zoning amendment (August 2026) would prohibit battery storage over 600 kWh in residential zones; the county plans public hearings in 2027. Board of Supervisors Minute Order No. 5 (September 11, 2024); SDCFPD Fire Protection Guidelines for BESS Facilities (September 17, 2026), item 9; County of San Diego, BESS zoning ordinance project page

Fire and building codes in force

How a project is permitted

Three pathways: (1) CPUC for public-utility BESS; (2) CEC AB 205 Opt-In (non-utility, requires community benefits); or (3) County Major Use Permit on a tiered framework by chemistry / size (MWh) / zone / project type.

Setbacks and spacing

Check a specific system

For a proposal or a system you're evaluating, answer a few questions in BESScheck: you get the rules that apply here, a checklist of what to ask, and the sources behind each line.