BESScheck

Battery storage rules: Mesa, AZ

Mesa's City Council set a 1,000 ft separation between battery energy storage facilities and residential uses on January 12, 2026 (Ordinance No. 5976).

Mesa: battery storage facilities 1,000 ft from homes

The City Council adopted a 1,000 ft separation from residential uses for battery energy storage facilities on January 12, 2026, by a 6–1 vote (Ordinance No. 5976). Council members said the distance would be revisited as technology and NFPA 855 evolve. Mesa City Council minutes, January 12, 2026, item 8-a (Ordinance No. 5976)

Fire and building codes in force

How a project is permitted

The state Line Siting Committee reviews "plants" of 100 MW or more, but the statute defines plants as thermal electric, nuclear or hydroelectric generating units; battery storage is not listed (A.R.S. 40-360). The Commission's Chair said its authority over non-thermal resources such as storage "hasn't been significantly updated since 1971" (ACC news release, October 3, 2025). Siting is therefore mostly local zoning. SB 1348 (2025), enacted as Chapter 99, lets cities and towns designate a reviewer for fire plans on municipal and private buildings, with a 60-day review deadline.

Check a specific system

For a proposal or a system you're evaluating, answer a few questions in BESScheck: you get the rules that apply here, a checklist of what to ask, and the sources behind each line.